Robin Hood Primary School & Nursery
VALUE:
£495,000
TIMESCALE:
8-weeks
“This project enhances Robin Hood Primary School & Nursery with new fencing, gates, and landscaping to boost safety, accessibility, and overall charm.”
Client
Robin Hood Primary School & Nursery
Value
£495,000
Duration
8-weeks
Type of Contract
JCT Design & Build
Consultant
Baily Garner LLP
Scope of Works
External improvement works including: new fencing, gates and landscaping design proposed with aim to improve the safeguarding, welfare and access to Robin Hood Primary and Nursery School.
Challenges
- A key priority for us was to make sure that we didn't disrupt the daily activities of the school and pupils.
- We did this through regular communication with the schools estate team making sure they knew what work we were carrying out, when and where we would be carrying it out and advising them of any areas that would not be available.
- Ground obstructions and booking in tarmac works during the busy summer holiday period.
Solutions
- Early engagement with the school ensured that we came up with a detailed construction management plan that worked around the school holiday club.
- We eliminated risk with ground obstructions by completing ground surveys before commencing the works.
- We ensured that we had booked our tarmac subcontractor in sufficiently early to ensure that there were no issues with delivery.
Why This Case Study
- Summer holiday school project involving external landscaping works which is extremely similar to what we will be completing at Discovery School
- This project involved new fencing which again is extremely similar to what we will be completing at Discovery School.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary