Hailsham Community College

VALUE:

£230,000

TIMESCALE:

6-weeks

“This project delivers a comprehensive electrical upgrade for Hailsham Community College, ensuring safety, efficiency, and a seamless installation experience tailored to the school’s unique needs.”

Client

Hailsham Community College

Value

£230,000

Duration

6-weeks

Type of Contract

JCT Design & Build

Consultant

East Sussex

Scope of Works

Full distribution upgrade including mains intake, switch gear, isolators and sub distribution boards. Emergency lighting install including design.

Challenges

Solutions

Why This Case Study

You may also like