Belverdere Infant School

VALUE:

£35,082.75

TIMESCALE:

2-weeks

“At Belvedere Infant School, we completed a swift and seamless upgrade of staff toilets over the Easter break, ensuring a refreshed and hygienic space ready for everyone’s return.”

Client

Belverdere Infant School

Value

£35,082.75
Duration

2-weeks

Type of Contract

JCT Design & Build

Consultant

The Pioneer Academy

Scope of Works

Strip out and clear from site existing toilet cubicles wash hand basins and cubicles. Strip out and clear from site existing vinyl flooring. Strip out ceiling tiles and clear from site, grid to remain. Hack off tiling and clear from site. Supply and lay new non-slip safety vinyl, from the Polysafe standard PUR range. Supply and install new hygienic ceiling tiles, from the British gypsum Gyprex Satinpar ceiling tiles.

Challenges

Solutions

Why This Case Study

You may also like

VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved

VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and

VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary

Scroll to Top