The Cavendish School

VALUE:

£365,000.00

TIMESCALE:

7-weeks

“Our project at Cavendish School successfully transformed the roof and interior spaces, ensuring a safe, well-insulated, and vibrant environment for students and staff, all completed smoothly over the summer break”

Client

Cavendish Education Trust

Value

£365,000.00

Duration

7-weeks

Type of Contract

JCT Intermediate Building
Contract 2016 Edition.

Consultant

Bailey Garner

Scope of Works

The proposed works are the replacement of the schools main pitched roof covering, including the provision of new insulation, battens, flashings, roofline goods and associated roofing components. The pitched roof will be renewed with a Marley System. The replacement of insulation shall conform to Part L of the Building Regulations, and ventilation shall conform to BS 5250.

Challenges

Solutions

Key Highlights

You may also like

VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved

VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and

VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary

Scroll to Top